Here’s a tentative schedule for the Library Addition project:

·         Measure building:  4-4-08

·         Input measurements into Cad: 4-18-08

·         Design Development:  5-9-08

·         Construction Documents:  7-04-08

·         Print/distribute bid documents to bidders:  7-11-08

·         Receive bids:  7-31-08

·         Start construction:  8-8-08

·         Move out of Library/start lease??  8-1-08 to 9-1-08

·         Complete construction: 7-1-09

·         Open renovated Library:  8-1-09